| Conceptualization, Development, Authority approvals |
2010-2013 |
Mining and excavation of the Monolith
- Main statue at Korakottai, Tamil Nadu
- Second statue (Adishesha), Korakottai, TN
|
2013-2015 |
Pedestal RCC pile foundation for the pedestal of the Mega Statue
- Pier cap
- Composite Main pillar
|
2017-2018 |
| Mega Transport Part-1 - Main Statue 500 tons over 350 Kms |
2018-2019 |
| Mega Transport Part-2 - Second Statue 180 tons over 350 Kms |
2020-2021 |
| Detailing, Work, Finishing Works in progress |
2020-2022 |
| Erection and installation of the statue on the pedestal |
2022--2023 |